How to run a project with agents in Hilbana, from decisions to the daily report: decide, specify, plan, build, audit by blocks and follow it every morning.
You can use a project tracker well or badly. This is the method we use ourselves to work with agents: every phase leaves its result inside Hilbana (docs, issues, comments), so the next phase, the next agent and the next person all start from the same place. Each phase has its prompt in the MCP and its shortcut in the Claude Code plugin.
The phases at a glance
| Phase | What happens | Prompt (shortcut) | Where it lands |
|---|---|---|---|
| 1. Decide | Settle the project’s decisions before writing anything | — (your own interview or meeting) | «Decisiones» doc |
| 2. Specify | One spec per area, reviewed against the decisions | especificar (/hilbana:especificar) |
«Spec · …» docs |
| 3. Plan | From specs to issues with dependencies | /hilbana:plan |
Issues linked to their spec |
| 4. Build | Each issue, from the queue to review | claim_next, finish, review |
Issues, closing comments |
| 5. Audit | When a block closes, check it against the specs | auditar_bloque (/hilbana:auditar-bloque) |
Comments and issues sent back |
| 6. Follow | The morning report for whoever runs the project | estado_proyecto (/hilbana:estado-proyecto) |
«Parte del proyecto» doc |
1. Decide
Before specifying, decide the things that shape the project: what’s in and what’s out, how it behaves in the hard cases, what gets reused. Each decision is one line of the project’s «Decisiones» (Decisions) doc:
D-012 · 2026-10-13 · Ana · accepted · The catalogue reaches the website unfiltered · origin WEB-41
How you get there is up to you: an interview with an agent that keeps asking until each point is settled, a meeting, or a prior document. Hilbana doesn’t impose a technique: what matters is that they end up in the doc, because the next phases read it. If you already have your own method, put its output there. See Project decisions.
2. Specify
With the decisions made, the especificar prompt proposes the areas and writes one
spec per area as a project doc (“Spec · Catalogue”, “Spec · Orders”…): goal, scope,
behaviour with cases, rules, permissions and acceptance criteria you can check, each
tied to the decision it comes from. A second review, by another agent if your client
can launch one, checks them against the decisions and brings out gaps and
contradictions. You approve them.
3. Plan
/hilbana:plan turns the specs into issues with dependencies. Each issue links its
spec in the agent context, and its Definition of Done comes from that spec’s acceptance
criteria, not from whatever comes to mind at the time. The ones that can start now land
in the agent queue.
4. Build
Each person or agent takes work from the queue (claim_next), does it and closes it
with finish: it verifies, leaves the issue in the status the workspace chose and
writes a closing comment for the reviewer. If something gets decided while building
that changes what was agreed, the comment ends with a «Decisiones:» section. Work
goes in blocks (a parent issue or a milestone), one at a time or in parallel.
5. Audit by blocks
When a block closes, auditar_bloque checks each issue against its spec, its
Definition of Done and the decisions, looks at the commit and grades the findings
(blocking, major or minor). It offers to send back what doesn’t pass with an actionable
comment; whoever had it assigned gets the “sent back to you” alert. An agent or a person
can run it: it proposes and leaves a trail, and whoever asked decides.
6. Follow the project every morning
Whoever runs the project asks for the report with estado_proyecto: the figures
from the Team tab (progress, pace, estimated end, who did what
each day), what each issue left done, the period’s decisions checked against the doc
(the ones that clash with something accepted are flagged) and what’s waiting for an
answer. Decisions get accepted or rejected from there, and the report is saved in a doc
so tomorrow’s one says what changed.
A real example
A websites project for the customers of a business software product, with two people coding and one running it:
- Decide: about two hundred decisions in the doc before the first spec, from a long interview with an agent.
- Specify: eight specs (instances, catalogue, templates, payments, orders…), each reviewed against the decisions.
- Plan: about three hundred issues in blocks per spec.
- Build: in the first week, 43 issues closed at 8.6 per working day, with the estimated end date visible from day one.
- Follow: every morning, before the meeting, whoever ran it already knew what was in review, what had gone back and which team decisions clashed with what was agreed, and settled them from the report itself.